Tapi Old Bridge |
|
Methodology for Repair
- Bituminous wearing coat and R.C.C wearing coat were removed by jack hammer using
compressed air
- All plates put on expansion joints were removed
- Study of damaged portion at the point of expansion joints and cross girders were
carried out
- Old cross girders were replaced by putting new cross girders with steel and concrete
insitu
- Broken portion of slab was recasted after welding extra Re-Bar as per design
- Designed expansion joints, finger type were installed as per specifications
- Hanging platform for scaffold work was erected from the top of the slab
- Removal of leached, spalled, honey combed concrete surface was done manually and
by Mechanical chippers
- Surface preparation was done by wire brushing and applying bond coat of Polymer
Modified Cement (PMC) slurry along with coating of Re-Bar with PMC bond Coat
- Extra steel Re-Bar was added to original Re-Bar whose diameter was below 80% of
original diameter and were coated by PMC slurry bond coat
- PMC mortar was applied to fill hollows and cavities manually with Masons and finished
to match the existing surface
- For repairing cracks V-Groove was made by mechanical cutter and filled with Epoxy
mortar
- And then wholes of 200mm depth were drilled at a distance of 300mm on both sides
of the girder
- With help of nipples low viscosity Epoxy Grout was grouted from top of the slab
with compressed air and Epoxy pump
- Existing damaged R.C.C parapet was repaired using Polymer Modified Cement (PMC)
Mortar
- Profile corrective course of PCC was laid on the top of the slab
- Water spout were fitted as per site requirement
- Bituminous mecadum leveling course was laid on the top and bridge was opened for
traffic
|
|
|
|
|
|
|
|